DOE and NIST Long Range Reactor Plans

Will Thomas, AIP, wthomas@aip.org

Momentum is building behind efforts to plan for the future of research reactors in the United States. Currently, there are two major reactor-based user facilities in the U.S. that provide researchers with access to high-flux neutron beams: the Department of Energy’s High Flux Isotope Reactor (HFIR) and the National Institute of Standards and Technology Center for Neutron Research (NCNR). Both reactors are about five decades old. Although they are expected to continue operating for many years, calls to develop a long-term strategy for them are beginning to propagate.

Much of the current discussion draws from a report the American Physical Society issued last year, spotlighting a shortage of capacity for neutron research in the U.S. relative to other global regions. Among its recommendations, the report urges the design and construction of a “new generation” of research reactor.

Work on a new reactor would only begin after an extensive planning process and, if approved, it would likely take many years to complete. In the meantime, the neutron research community must deal with a more immediate problem: the effects of extended unplanned shutdowns at both HFIR and NCNR. While unrelated to the facilities’ long-term prospects, the situation has put already highly subscribed resources for neutron research under unusually acute strain.

DOE asks advisory committee for reactor study

At its meeting in March, the Basic Energy Sciences Advisory Committee (BESAC) received a charge from DOE asking it to assess “the scientific justification for a U.S. domestic high-performance reactor-based research facility, taking into account current international plans and existing domestic facility infrastructure.”

The study is to explore the significance of science that can be performed using a research reactor and to consider the full range of capabilities that reactors can provide. These include neutron-beam experiments as well as materials testing by irradiation, radioisotope production, neutron activation for trace element analysis, and dark matter research. The study will also consider the role of reactor-based neutron sources versus spallation neutron sources. DOE is currently planning major upgrades to its Spallation Neutron Source (SNS) facility that will increase both its capabilities and its capacity.

DOE stipulates the study should also offer advice regarding the department’s “long-term strategy concerning HFIR.” The charge explains, “With HFIR entering its sixth decade, its long-term future requires careful thought and planning, especially in the context of the U.S. domestic high-performance neutron research facilities.” It notes that one avenue the study should explore is whether there are “feasible upgrade paths for HFIR to provide world-leading capabilities … well into the future.”

The charge also asks BESAC to consider whether low enriched uranium (LEU) could be used in a reactor without significantly diminishing its utility. Currently, HFIR and many other high-performance research reactors around the world use highly enriched uranium (HEU). It has long been U.S. policy to tamp down the use of HEU to mitigate the risk of its theft by rogue actors who could use it to make nuclear weapons. However, efforts to convert HEU reactors, including HFIR, to use LEU have been inhibited by the difficulty of fabricating suitable LEU fuels.

In considering upgrades to HFIR, BESAC is instructed to look to the experience of Europe’s premier reactor-based user facility, the Institut Laue-Langevin (ILL) in Grenoble, France. Commissioned in 1972, the facility underwent a series of upgrades from 2000 to 2018 and is now beginning a second series scheduled to continue through 2023. Although ILL agreed to convert to LEU 20 years ago, the facility continues to use HEU fuel and there are no immediate plans to abandon it.

There would be fewer difficulties in fabricating LEU fuel for new reactors if they are specifically designed to accommodate it, as the APS report recommends. The U.S. has not seriously considered building a new multipurpose high-performance research reactor since the 1990s, when DOE planned a large, HEU-fueled reactor called the Advanced Neutron Source that was ultimately cancelled in the face of rising cost estimates. The APS and BESAC reports could prepare the way for a new proposal to be put on the table.

National Academies panel broaches NIST reactor replacement

A recommendation for a new reactor would also have to take into account the future of NCNR, which underwent a routine National Academies assessment last year. While the assessment found the facility is well run and delivers a high return on investment, it stated, “The nuclear reactor on which the NCNR depends is 50 years old, and as a matter of simple prudence, a plan needs to be developed that will ensure that NCNR users have the neutrons they need into the indefinite future.”

The assessment pointed to three options for the long-term future of NCNR: continuing to operate its existing reactor, upgrading it, or replacing it completely. Suggesting the first two options are “inferior” to the third, the assessment points to an internal NCNR report from 2017 that found a new reactor would cost about $1 billion and take more than 15 years to complete. “A project of this magnitude will not be undertaken without a substantial planning effort and support from the neutron and the general scientific communities,” it observed. Accordingly, it recommended NCNR “commission a detailed assessment of the current facility and begin the conceptual design of a new reactor.”

NIST has not announced a response to the recommendation, but at the meeting of its primary advisory panel in June, NIST Director Walter Copan said that the agency is working on jointly sponsoring a National Academies study with DOE and the National Science Foundation. In Congress, Rep. Randy Weber (R-TX) is now sponsoring a bill that, among its other provisions, would endorse efforts to plan for NCNR’s future.

Reactor shutdowns hamper neutron research community

Even as planning begins for the long-term future of HFIR and NCNR, both facilities have recently had to deal with the short-term effects of unplanned shutdowns. NCNR was offline for more than one month at the beginning of this year due to the partial shutdown of the federal government. According to a story in the Los Angeles Times, during that time more than 100 experiments were cancelled, causing considerable disruption to the facility’s users. Schedule reshuffling continued even following the restoration of operations on Feb. 5 in order to accommodate cancelled experiments.

HFIR, meanwhile, has been shut down since November, following the detection of slightly elevated radiation levels in its primary coolant system following a routine refueling. Harriet Kung, director of DOE’s Basic Energy Sciences program, told BESAC that 45 of the 540 plates within the reactor’s newly installed fuel elements were discovered to be “deflected.” She reported that no radioactivity was released from the reactor and no personnel had been exposed. The reactor facility itself was undamaged.

In an update on Feb. 14, Paul Langan, who directs the neutron sciences program at Oak Ridge, reported the incident is still under review and procedures are being developed to prevent it from happening again. Kung said that 252 experiments will have been cancelled by May 1 and that Oak Ridge is aiming to restore operations by the end of the fiscal year on Sept. 30.

It remains unclear exactly how much the HFIR shutdown is affecting researchers’ ability to obtain time at SNS and NCNR, which were already heavily subscribed. Langan told BESAC that Oak Ridge has worked to accommodate HFIR users at SNS where possible, but that not all experiments are transferrable. Another question is how the shutdown is affecting the supply chains of the isotopes HFIR produces, which are employed in medical applications and as fuel on interplanetary science missions, among other uses.